Site under construction — content is updated periodically.
Wazawa Green Energy Limited logo Wazawa Green Energy LimitedPowering for a Sustainable Tomorrow Contact Us
Overview  /  Project
The Project

A 12.5 MW biomass power plant in Sumbawanga, Rukwa Region

Abundant fuel, transformational grid infrastructure arriving in 2027, and chronic unmet demand — the three factors that make Rukwa the right place for firm renewable power.

Executive summary

Secure, locally-sourced fuel for a 25-year plant life

The project is strategically located in Rukwa Region, one of Tanzania's most agriculturally productive regions, producing approximately 1.7 million tons of crops annually. The region generates over 1.87 million tons of agricultural residues per year — far exceeding the plant's annual biomass requirement of 100,000–120,000 tons. This ensures a secure, locally-sourced and competitively-priced fuel supply for the entire 25-year plant lifecycle.

Rukwa Region is currently being connected to Tanzania's national grid through the 400 kV Tanzania–Zambia (TAZA) Power Transmission Project, with full grid integration expected by February 2027. This milestone dramatically improves the power evacuation prospects of the plant, transitioning the region from an energy-deficit periphery to a fully-integrated node in the national transmission network.

Key parameters

Project Name
Wazawa Green Energy Limited — 12.50 MW Biomass Power Project
Location
Sumbawanga, Rukwa Region, Tanzania
Installed Capacity
12.50 MW
Sale to TANESCO
10 MW at the interconnection point of TANESCO sub-station
Technology
Boiler + Steam Turbine (CFBC)
Primary Fuel
Rice husk, maize cobs and stalks, sunflower husk stalks, cotton stalk, forestry residues
Annual Generation
~72 GWh (at 80% Plant Load Factor)
Annual Biomass Requirement
100,000 – 120,000 tonnes/year
Plant Design Life
25 years
Grid Connection
33 kV / 66 kV interconnection with TANESCO (Sumbawanga Substation)
Power Offtake
Power Purchase Agreement with TANESCO Under progress
Implementation Period
18–20 months
Employment (Direct)
60 permanent + 200 during construction
Employment (Indirect/Induced)
500+ jobs across supply chain and community
Carbon Credits (projected)
~50,000–60,000 tCO₂e/year
Why Rukwa

Three factors converge in the southwestern highlands

Rukwa Region represents a convergence of agricultural abundance, transformational grid infrastructure and chronic unmet demand — making it an ideal location for a biomass power project.

Agricultural abundance

Rukwa produces approximately 1.7 million tons of crops annually, generating 1.87 million tons of harvestable biomass residues — more than sufficient for a 12.50 MW plant. Maize alone contributes ~929,000 tons.

Improving grid infrastructure

The 400 kV TAZA transmission line is under construction, with Rukwa's full grid integration scheduled for February 2027 — unlocking power evacuation capacity to the national grid and the Southern African Power Pool.

Unmet energy demand

Despite the Sumbawanga substation's 30 MVA capacity and cross-border Zambian imports, the region suffers chronic power shortages affecting industry, agriculture and households. Only 184 of 339 villages (54%) are electrified.

The game-changer

TAZA 400 kV Transmission Project

The Tanzania–Zambia (TAZA) 400 kV high-voltage transmission project will connect Rukwa to the Tanzania national grid via the Iringa → Mbeya → Rukwa corridor. Once complete, power generated at Sumbawanga can be evacuated to the national grid and the Southern African Power Pool.

Transmission Voltage
400 kV
Route
Iringa → Mbeya → Rukwa (Sumbawanga)
Purpose
Connect Rukwa to national grid and SAPP
Expected Completion
February 2027
Impact on Biomass IPP
Full power evacuation to the national grid
Grid Connection Point
Sumbawanga Substation (33 kV / 66 kV)

Tanzania's generation mix — why firm biomass matters

Installed capacity stood at approximately 4,532.66 MW at the end of 2025, including 67 MW of cross-border imports. The mix remains heavily weighted toward hydropower and natural gas, creating well-documented vulnerabilities. Unlike solar and wind, biomass-fuelled generation is dispatchable — it generates reliably 24 hours a day, 365 days a year, providing firm capacity rather than intermittent output.

Regulatory & policy framework

Electricity Act (2008)

Legal framework for IPPs, licensing and grid access in Tanzania.

Small Power Projects Framework (2017)

Standardised PPA structure for renewable plants exporting up to 10 MW at the sub-station interconnection point.

Renewable Energy Feed-in Tariff (REFiT)

Government-mandated framework for renewable energy offtake.

National Renewable Energy Policy (2015)

Target of 10 GW renewable energy by 2030.

NEMC Environmental Clearance

Required under the Environmental Management Act (2004).

EWURA Licensing

Energy and Water Utilities Regulatory Authority generation and trading licence.

Biomass Resource

17× fuel coverage from three districts within a 70 km radius

The plant's annual biomass requirement of 100,000–120,000 tons represents only 32–65% of the collectable biomass available from Sumbawanga District alone — confirming ample fuel security without competing with food security or existing biomass uses.

DistrictAdmin CentreKey CropsAnnual Crop ProductionResidue PotentialCollectable Biomass
SumbawangaSumbawangaMaize, Rice, Sunflower, Beans~560,000 t~809,000 t/yr80,000–120,000 t/yr
NkasiNamanyereMaize, Sorghum, Rice, Sunflower~390,000 t~608,000 t/yr60,000–90,000 t/yr
KalamboMataiMaize, Rice, Sorghum, Sunflower~290,000 t~455,000 t/yr45,000–68,000 t/yr
Region TotalAll major cereals, oilseeds~1.7 million t~1.872 million t/yr185,000–278,000 t/yr

Collectable biomass vs plant requirement ('000 t/yr)

Collectable estimates use conservative Residue-to-Product Ratios with a 10–15% collection efficiency factor to account for competing uses (soil carbon, livestock fodder, domestic cooking fuel) — consistent with FAO and MNRE Biomass Resource Atlas methodology.

Fuel supply strategy

  • Long-term farmer cooperative agreements — multi-year supply contracts with registered cooperatives in Sumbawanga and Nkasi districts for rice husk and maize cob supply.
  • Agro-processing industry offtake — agreements with rice mills, sunflower oil processors and cotton ginning facilities for continuous processing residues.
  • Biomass aggregation centres — 4–6 decentralised collection and pre-processing centres within a 70 km radius, equipped with chippers, balers and moisture-testing equipment.
  • Inventory buffer — covered storage maintaining 120–150 days of fuel inventory, insulating operations against seasonal variability.
  • Indexed supply contracts — annual adjustment clauses protecting both farmer income and plant operations.
Residue TypeRPRPrimary DistrictAnnual Residue (Sumbawanga)Calorific Value (kcal/kg)
Maize stalk & cob1.5Sumbawanga, Nkasi525,000 t3,500–4,000
Rice straw1.5Sumbawanga180,000 t3,200–3,800
Rice husk0.2Sumbawanga, Nkasi24,000 t3,400–3,800
Sunflower stalk2.0All districts80,000 t3,600–4,200
Sorghum straw1.5Nkasi, Kalambo105,000 t3,300–3,900
Cotton stalk2.5SeasonalSupplementary3,800–4,500
Forestry residuesVariableAll districtsSupplementary4,000–5,000
Implementation Plan

Commercial operation in 18–20 months

  1. Phase 0

    Pre-Development Completed

    Legal incorporation; site identification; resource assessment; feasibility study; concept note preparation. Company incorporated; concept note ready; site identified.

  2. Phase 1

    Development Months 1–6

    Land acquisition (25–30 acres); NEMC environmental screening; EWURA licence application; TANESCO PPA term sheet (under progress); lender mandates. Land secured; EIA commenced.

  3. Phase 2

    Closure Months 4–8

    Full EIA completion; TANESCO PPA signing; partner and lender agreements; EPC contract award. PPA executed; project closure achieved.

  4. Phase 3

    Engineering & Procurement Months 6–12

    Detailed engineering; boiler and turbine equipment order; long-lead item procurement. Equipment orders placed; civil drawings approved.

  5. Phase 4

    Construction Months 8–18

    Civil and structural works; equipment installation; electrical works; switchyard construction. Plant physically complete; ready for testing.

  6. Phase 5

    Commissioning Months 18–20

    Equipment testing; trial runs; synchronisation with grid; performance guarantee tests. Commercial Operation Date (COD) achieved.

  7. Phase 6

    Operations Month 20 → Year 25

    Full commercial operation; PPA deliveries; O&M; carbon credit registration and verification. Stable 10 MW output to the grid.

AgreementCounterpartyDurationStatus / Key Terms
Power Purchase Agreement (PPA)TANESCO25 years (proposed)Under progress
Biomass Supply AgreementsFarmer cooperatives, agro-processors, aggregators5-year renewableMinimum supply guarantee; indexed pricing; quality specifications
EPC ContractQualified biomass power EPC contractor (India/international)18 monthsFixed scope; performance guarantee; liquidated damages for delay
O&M AgreementSpecialist O&M provider (first 3 years)3 years initial, renewablePerformance-based; availability guarantee ≥85%
Grid Connection AgreementTANESCOLife of plant33/66 kV interconnection; metering; balancing
Water Abstraction PermitTanzania Basin Water Board (Rukwa)Annual, renewable0.8–1.2 m³/MWh; groundwater borewell; surface water supplementary
Land Lease / TitleSumbawanga District Council / MLHHSD25 years + renewal25–30 acres; freehold or long-term lease; registered title
Risk Assessment & Mitigation

Every material risk mapped to a structured mitigation

Fuel Supply

P: Low–Med · I: Low

Shortage of biomass in dry season or supply chain failure

Diversified procurement from 3+ districts; 120–150 day fuel buffer; multi-crop fuel mix; long-term cooperative contracts

Offtake

P: Low · I: High

Delays in PPA conclusion or in offtaker payments

PPA structured with appropriate security mechanisms; development-partner support; EWURA regulatory protection

Grid Evacuation

P: Med · I: High

Delay in TAZA 400 kV line completion beyond 2027

Commissioning timed to grid completion; interim offtake to local industrial buyers; TANESCO direct interconnection agreement

Construction Delay

P: Med · I: Med

EPC contractor delay; equipment shipping; permitting obstacles

EPC contract with LD clauses; long-lead equipment pre-ordered; parallel permitting track

Fuel Cost Escalation

P: Low–Med · I: Med

Biomass procurement costs above projections

Indexed supply contracts; own aggregation centres reduce intermediary costs

Technology Performance

P: Low · I: Med

Boiler performance below design; lower efficiency

Proven CFBC technology from experienced manufacturer; OEM performance guarantee; O&M specialist for first 3 years

Regulatory Change

P: Low · I: High

Changes in tariff, tax or renewable energy policy

Stabilisation agreement with TANESCO/Government; international arbitration clause in PPA

Water Supply

P: Low–Med · I: Med

Seasonal water shortage affecting boiler operations

Borewell as primary source; 7-day storage reservoir; dry-season supply plan; water recycling

Social Acceptance

P: Low · I: Med

Community resistance to land acquisition or development

Community consultation from outset; transparent compensation; benefit sharing — employment priority, local procurement

Statutory approvals & licences

Approval / LicenceIssuing AuthorityTimelineStatus
Environmental & Social Impact Assessment (ESIA)National Environment Management Council (NEMC)3–4 monthsTo be initiated at Phase 1
Generation LicenceEnergy and Water Utilities Regulatory Authority (EWURA)3–4 monthsTo be applied
Power Purchase Agreement (PPA)TANESCO4–8 monthsUnder progress
Grid Connection AgreementTANESCO — Grid DepartmentConcurrent with PPATo be applied
Land Allocation / Right of OccupancyMLHHSD / Sumbawanga DC3–4 monthsSite identification completed
Water Abstraction PermitRufiji Basin Water Board (jurisdiction TBC)2–3 monthsTo be applied after site confirmation
Building PermitSumbawanga District Council1–2 monthsTo be applied at detailed design
Import Duty Exemptions (equipment)Tanzania Revenue Authority (TRA)2–3 monthsApplicable under Renewable Energy Incentives
Carbon Project ValidationGold Standard / Verra (VCS)6–12 months (post-COD)To be initiated at commissioning